Answering: “Why is it important to have a stakeholder communication plan and communicate with stakeholders outside of the Sprint Review?”

Table of Contents

Importance of Stakeholder Communication Plan

Effective communication with stakeholders is crucial for the success of any Scrum project. A well-defined stakeholder communication plan ensures that all relevant parties are informed, engaged, and aligned with the project goals and progress.

Exam Question

Why is it important to have a stakeholder communication plan and communicate with stakeholders outside of the Sprint Review?
(choose the best answer)
A. Stakeholders are the ultimate decision makers and need to be communicated with often.
B. It is not important. All stakeholder conversations should be a collaborative discussion during the Sprint Review.
C. It promotes transparency and the opportunity to adapt the Product Backlog.
D. Stakeholders require continual budget and project status for transparency.

Correct Answer

C. It promotes transparency and the opportunity to adapt the Product Backlog.

Explanation

Correct Answer

C. It promotes transparency and the opportunity to adapt the Product Backlog:
Communicating with stakeholders outside of the Sprint Review promotes transparency and keeps them informed about the progress and any changes in the project. Regular communication allows the Scrum Team to receive continuous feedback, which can then be used to adapt and refine the Product Backlog. This ensures that the product evolves to meet stakeholder needs and expectations effectively.

Why the Other Options Are Incorrect

A. Stakeholders are the ultimate decision makers and need to be communicated with often:
While stakeholders’ input is valuable, they are not necessarily the ultimate decision-makers in a Scrum framework. The Product Owner makes decisions about the Product Backlog prioritization.

B. It is not important. All stakeholder conversations should be a collaborative discussion during the Sprint Review:
Limiting stakeholder communication to only Sprint Reviews can result in missed opportunities for timely feedback and necessary adjustments. Continuous communication is key to agility.

D. Stakeholders require continual budget and project status for transparency:
While budget and project status updates are important, the primary purpose of ongoing communication is to ensure the product meets stakeholder needs and to adapt the Product Backlog as necessary.

Relevance to the PSPBM Skills Exam

Understanding the importance of stakeholder communication is crucial for the PSPBM Skills exam. It highlights the necessity of maintaining transparency and adaptability in the Product Backlog, ensuring that the Scrum Team can deliver maximum value.

Key Takeaways

  • Continuous communication with stakeholders promotes transparency and allows for timely feedback.
  • Regular updates enable the adaptation and refinement of the Product Backlog, ensuring alignment with stakeholder needs.
  • Effective stakeholder communication is a fundamental aspect of successful Product Backlog management.

Conclusion

A stakeholder communication plan is essential for maintaining transparency and adaptability in Scrum projects. For more information on preparing for the PSPBM Skills exam, visit our Professional Scrum Product Backlog Management Skills PSPBMâ„¢ Exam Prep.