Answering: “Who should make sure everyone on the Scrum Team does their tasks for the Sprint?”

Table of Contents

Ensuring Task Completion in a Scrum Team

In a Scrum Team, accountability and responsibility are distributed among all team members. This collaborative approach is central to the effectiveness of Scrum.

Exam Question

Who should make sure everyone on the Scrum Team does their tasks for the Sprint? (choose the best answer)

  • A. The Project Manager.
  • B. The Product Owner.
  • C. The Scrum Master.
  • D. The Scrum Team.
  • E. All of the above.

Correct Answer

D. The Scrum Team.

Explanation

Why D is Correct

D. The Scrum Team:

In Scrum, the team is self-managing, meaning they are collectively responsible for managing their own work and ensuring that all tasks are completed. The entire Scrum Team holds each other accountable, fostering a collaborative environment where everyone is committed to achieving the Sprint Goal. This shared responsibility ensures that all team members are engaged and contribute to the success of the Sprint.

Why A, B, C, and E are Incorrect

A. The Project Manager:

Scrum does not include the role of a Project Manager. Responsibilities typically associated with project management are distributed among the Scrum roles, with a strong emphasis on team self-management and collaboration.

B. The Product Owner:

The Product Owner is responsible for maximizing the value of the product and managing the Product Backlog, not for managing individual tasks or ensuring team members complete their work.

C. The Scrum Master:

The Scrum Master facilitates Scrum processes and helps remove impediments, but they do not manage the tasks or ensure that everyone completes their work. Their role is more about coaching and supporting the team in their self-management.

E. All of the above:

This option is incorrect because it implies roles outside of the Scrum framework (like the Project Manager) and misunderstands the distributed nature of accountability in Scrum.

Key Points

  • Self-Management: The Scrum Team collectively manages their tasks, ensuring that all work necessary to meet the Sprint Goal is completed.
  • Shared Accountability: All team members are responsible for holding each other accountable, fostering a collaborative and committed team environment.
  • Role Clarity: Each role in Scrum has specific responsibilities, with the Scrum Team as a whole responsible for task completion.

Responsibilities in Scrum

  • Product Owner: Maximizes the value of the product by ensuring the Product Backlog is well-ordered and refined to the level needed.
  • Scrum Master: Coaches the team in Scrum practices, removes impediments, and facilitates team events to ensure productivity and adherence to Scrum principles.
  • Developers: Collaborate to complete all tasks necessary to deliver a potentially shippable Increment, maintaining quality and continuously improving their processes.

Relevance to the PSM I Exam

Understanding the distributed nature of responsibility and the importance of self-management in Scrum is crucial for the PSM I exam. This knowledge emphasizes the collaborative and accountable environment that Scrum aims to create, where every team member is responsible for the success of the Sprint.

Conclusion

In a Scrum Team, it is the collective responsibility of the team to ensure that all tasks are completed. This self-managing approach fosters collaboration, accountability, and a strong commitment to achieving the Sprint Goal.

For comprehensive preparation and practice exams, check out PSM I Exam Prep to enhance your understanding and application of Scrum principles.

Sign up for more exam tips and discounts



You cannot copy content of this page

$35 Exam Preps

Sale Ending Soon

Day
Hour
Min
Sec
Offer Expired
Add Your Heading Text Here