Exam Question
Who can cancel a Sprint?
(choose the best answer)
A. The Stakeholders.
B. The Scrum Master.
C. The Scrum Team.
D. The Product Owner.
Correct Answer
D. The Product Owner.
Explanation
Correct Answer
D. The Product Owner:
The Product Owner is the only role with the authority to cancel a Sprint. This is because the Product Owner is responsible for maximizing the value of the product and may determine that the Sprint Goal is no longer viable or relevant. If a Sprint Goal becomes obsolete, it is the Product Owner’s responsibility to cancel the Sprint to ensure that the Scrum Team does not waste effort on work that no longer aligns with the product’s value objectives.
Incorrect Answers
A. The Stakeholders:
Stakeholders do not have the authority to cancel a Sprint. Their role is to provide input and feedback, but they do not manage the Sprint process.
B. The Scrum Master:
While the Scrum Master facilitates the Scrum process and ensures that the team adheres to Scrum principles, they do not have the authority to cancel a Sprint.
C. The Scrum Team:
The Scrum Team collaborates to achieve the Sprint Goal but does not have the authority to cancel the Sprint. This decision is reserved for the Product Owner.
Responsibilities in Scrum
- Product Owner: The Product Owner is accountable for maximizing the value of the product. They have the authority to cancel a Sprint if the Sprint Goal becomes obsolete or irrelevant.
- Scrum Master: The Scrum Master facilitates Scrum events and helps the team adhere to Scrum principles but does not cancel Sprints.
- Developers: The Developers focus on completing the work planned for the Sprint and do not have the authority to cancel the Sprint.
Relevance to the PSPO I Exam
Understanding the authority and responsibilities associated with canceling a Sprint is crucial for the PSPO I exam. This knowledge ensures that candidates can effectively manage the Sprint process and make informed decisions about the continuation or cancellation of Sprints.
Key Takeaways
- Only the Product Owner has the authority to cancel a Sprint.
- The Product Owner cancels a Sprint if the Sprint Goal becomes obsolete or irrelevant.
- Stakeholders, Scrum Master, and Developers do not have the authority to cancel a Sprint.
Conclusion
The authority to cancel a Sprint lies solely with the Product Owner, ensuring that the Scrum Team remains focused on delivering maximum value. By understanding this principle, you can better appreciate the roles and responsibilities within the Scrum framework. For more information on preparing for the PSPO I exam, visit our PSPO I Exam Prep.