Developers’ Accountabilities in Scrum
In Scrum, Developers have specific accountabilities that ensure the successful delivery of the product Increment each Sprint. Understanding these accountabilities is crucial for maintaining a high-performing Scrum Team.
Exam Question
Which of the following are the Developers accountable for? (choose the best two answers)
- A. Organizing the work required to meet the Sprint Goal.
- B. Reporting productivity.
- C. Creating a plan for the Sprint, the Sprint Backlog.
- D. Selecting the Product Owner.
Correct Answers
A. Organizing the work required to meet the Sprint Goal.
C. Creating a plan for the Sprint, the Sprint Backlog.
Explanation
Why A and C are Correct
A. Organizing the work required to meet the Sprint Goal: Developers are responsible for organizing and managing the work necessary to achieve the Sprint Goal. This includes determining how to complete the tasks and collaborating to overcome any challenges that arise during the Sprint.
C. Creating a plan for the Sprint, the Sprint Backlog: During Sprint Planning, Developers create the Sprint Backlog, which includes a plan for how they will deliver the selected Product Backlog items and meet the Sprint Goal. This involves detailed task breakdowns and estimations to ensure they can achieve their objectives.
Why B and D are Incorrect
B. Reporting productivity: While transparency and communication about progress are important, reporting productivity is not a specific accountability of the Developers. Productivity tracking can be part of team metrics but is not a primary responsibility.
D. Selecting the Product Owner: The selection of the Product Owner is not the responsibility of the Developers. The Product Owner is typically appointed by the organization based on their expertise and ability to maximize the value of the product.
Key Points
- Sprint Goal: Developers are accountable for organizing their work to meet the Sprint Goal.
- Sprint Backlog: Developers create and manage the Sprint Backlog, detailing how they will achieve the Sprint Goal.
Responsibilities in Scrum
- Product Owner: Ensures the Product Backlog is ordered and refined to maximize value and align with the team’s capacity.
- Scrum Master: Facilitates Scrum events, removes impediments, and helps teams adhere to Scrum principles.
- Developers: Collaborate to create the Sprint Backlog, organize the work to meet the Sprint Goal, and ensure all tasks meet the Definition of Done.
Relevance to the PSM I Exam
Understanding the specific accountabilities of Developers is crucial for the PSM I exam. This knowledge highlights the importance of self-management and collective ownership in achieving the Sprint Goal and delivering high-quality Increments.
Conclusion
Developers are accountable for organizing the work required to meet the Sprint Goal and creating the Sprint Backlog. These responsibilities ensure that the team can effectively plan and execute their tasks to deliver a potentially shippable Increment each Sprint.