Starting the Second Sprint
Understanding the start of the second Sprint is essential for managing the flow of work and ensuring continuous delivery of value. This article explores when the second Sprint should begin according to Scrum principles.
Exam Question
When does the second Sprint start?
(choose the best answer)
A. Immediately after the first Sprint.
B. After the Product Backlog items for the second Sprint have been selected.
C. Once the architectural changes for the second Sprint are approved by the senior architect.
D. After the customer completes acceptance testing of the first Sprint.
Correct Answer
A. Immediately after the first Sprint.
Explanation
Correct Answer
A. Immediately after the first Sprint:
According to Scrum, Sprints are continuous with no breaks in between. The next Sprint starts immediately after the conclusion of the previous Sprint, ensuring a steady flow of work and consistent progress.
Incorrect Answers
B. After the Product Backlog items for the second Sprint have been selected:
The selection of Product Backlog items happens during Sprint Planning, which marks the beginning of the Sprint. Thus, the Sprint doesn’t start after selecting items but immediately after the previous one ends.
C. Once the architectural changes for the second Sprint are approved by the senior architect:
Scrum promotes self-managing teams where Developers decide on the necessary work without requiring approvals from external authorities like a senior architect.
D. After the customer completes acceptance testing of the first Sprint:
Customer acceptance testing is not a prerequisite for starting the next Sprint. Continuous delivery and iterative progress mean the next Sprint starts immediately, regardless of customer acceptance testing status.
Responsibilities in Scrum
- Product Owner: The Product Owner is responsible for managing the Product Backlog, ensuring it is ready for Sprint Planning. They work closely with the Developers to prepare for the next Sprint.
- Scrum Master: The Scrum Master facilitates the transition from one Sprint to the next, ensuring that the team adheres to Scrum principles and that Sprint Planning occurs promptly.
- Developers: The Developers are responsible for planning and executing the work for each Sprint. They participate in Sprint Planning immediately following the conclusion of the previous Sprint.
Relevance to the PSPO I Exam
Understanding the continuity of Sprints is crucial for the PSPO I exam. This knowledge ensures that candidates appreciate the importance of maintaining a steady workflow and adhering to Scrum’s iterative nature, which is fundamental for successful product development.
Key Takeaways
- Sprints are continuous with no breaks in between.
- The next Sprint begins immediately after the previous one ends.
- Scrum promotes a steady flow of work and consistent progress.
Conclusion
The immediate start of the second Sprint after the first ensures a continuous flow of work and maintains momentum in product development. Understanding this principle is essential for effective Scrum practice and for preparing for the PSPO I exam. For more information on preparing for the PSPO I exam, visit our PSPO I Exam Prep.