Cancellation of a Sprint by Developers
In Scrum, the decision to cancel a Sprint is a significant one and typically lies within the authority of the Product Owner. Here is an analysis of whether Developers can cancel a Sprint and under what conditions this might occur:
Exam Question
When can Developers cancel a Sprint? (choose the best answer)
- A. When the Product Owner is absent too often.
- B. When functional expectations are not well understood.
- C. They cannot. Only Product Owners can cancel Sprints.
- D. When the selected Product Backlog items for the Sprint become unachievable.
- E. When a technical dependency cannot be resolved.
Correct Answer
C. They cannot. Only Product Owners can cancel Sprints.
Explanation
Why C is Correct
In Scrum, the authority to cancel a Sprint rests solely with the Product Owner. This decision is typically based on whether the Sprint Goal becomes obsolete due to changes in market conditions, business priorities, or significant shifts in project direction. While Developers play a crucial role in executing the Sprint and can raise concerns about feasibility and challenges, the final decision to cancel the Sprint lies with the Product Owner.
Key Points
- Authority of the Product Owner: The Product Owner is responsible for maximizing the value of the product and has the authority to cancel a Sprint if it no longer delivers value or aligns with the project goals.
- Feasibility Concerns: Developers can communicate any issues or challenges that may arise during the Sprint, but they do not have the authority to cancel it.
- Collaboration: Effective communication and collaboration between the Product Owner and Developers are essential to address any issues that may arise during the Sprint.
Roles and Responsibilities in Scrum
- Product Owner: Has the authority to cancel the Sprint if the Sprint Goal becomes obsolete or if continuing the Sprint no longer delivers value.
- Scrum Master: Facilitates communication between the Product Owner and Developers, helping to resolve any issues that may arise during the Sprint.
- Developers: Identify and communicate challenges, impediments, and feasibility concerns to the Product Owner but do not have the authority to cancel the Sprint.
Relevance to the PSM I Exam
Understanding the roles and responsibilities regarding Sprint cancellation is crucial for the PSM I exam. This knowledge helps candidates appreciate the importance of the Product Owner’s authority and the collaborative nature of addressing challenges within the Scrum Team.
Conclusion
Developers cannot cancel a Sprint. Only the Product Owner has the authority to make this decision, typically based on whether the Sprint Goal remains viable and valuable. Effective communication and collaboration within the Scrum Team are essential to address any issues that may arise during the Sprint.
For comprehensive preparation and practice exams, check out PSM I Exam Prep to enhance your understanding and application of Scrum principles.