Answering: “Select two ways in which leaving work undone at the end of the Sprint impacts transparency.”

Impact of Undone Work on Transparency

In a Scrum framework, ensuring that all work is completed by the end of each Sprint is critical for maintaining transparency. When work is left undone, it can have significant impacts on the team’s ability to accurately assess the state of the product and plan future work effectively.

Exam Question

Select two ways in which leaving work undone at the end of the Sprint impacts transparency.
(choose the best two answers)
A. The lack of transparency leads to false assumptions about the current state of the product.
B. As development progresses, the product becomes more difficult to integrate, which results in future work being slowed down in unpredictable ways.
C. When calculated and estimated, the total amount of undone work shows exactly how long until the Product Owner can release the Increment.
D. Undone work is acceptable as long as the Developers factor it into their future Sprint Plans.

Correct Answers

A. The lack of transparency leads to false assumptions about the current state of the product.
B. As development progresses, the product becomes more difficult to integrate, which results in future work being slowed down in unpredictable ways.

Explanation

Correct Answers

A. The lack of transparency leads to false assumptions about the current state of the product:
When work is left undone at the end of a Sprint, it creates a false sense of progress and completeness. Stakeholders, including the Product Owner, may assume that the product is in a better state than it actually is. This can lead to misguided decisions and a lack of trust in the Scrum process.

B. As development progresses, the product becomes more difficult to integrate, which results in future work being slowed down in unpredictable ways:
Undone work often means that parts of the product are not fully integrated or tested. This can create technical debt, where the product becomes increasingly difficult to work with over time. As more features are added, the complexity and instability of the product grow, slowing down future development and making integration more challenging.

Why the Other Options Are Less Effective

C. When calculated and estimated, the total amount of undone work shows exactly how long until the Product Owner can release the Increment:
This option assumes that undone work can be perfectly measured and planned for, which is rarely the case. The unpredictable nature of undone work means that it can introduce unforeseen issues that disrupt planning and estimation.

D. Undone work is acceptable as long as the Developers factor it into their future Sprint Plans:
While it is possible to plan for undone work, accepting it as a norm undermines the principle of delivering a potentially shippable Increment each Sprint. This can erode the discipline of the Scrum Team and compromise the integrity of the Scrum framework.

Importance of Transparency

Transparency is a cornerstone of Scrum, enabling all stakeholders to have a clear and accurate understanding of the product’s state. By ensuring that all work is completed within the Sprint, the Scrum Team maintains this transparency, allowing for informed decision-making and effective planning.

Relevance to the SPS Exam

Understanding the impact of leaving work undone on transparency is crucial for the SPS exam. It highlights the importance of maintaining a clear and accurate picture of the product’s state, which is essential for effective scaling of Scrum practices.

Key Takeaways

  • Leaving work undone at the end of a Sprint can create false assumptions about the product’s state and hinder future development.
  • Ensuring that all work is completed within the Sprint is essential for maintaining transparency and trust in the Scrum process.
  • Addressing and resolving technical debt promptly helps maintain the integrity and stability of the product.

Conclusion

Maintaining transparency is essential for the success of any Scrum initiative, especially when scaling Scrum with a Nexus framework. By understanding and addressing the impacts of leaving work undone, Scrum Teams can ensure they deliver high-quality, integrated Increments every Sprint. For more information on preparing for the SPS exam, visit our Scaled Professional Scrum SPSâ„¢ Exam Prep.

Table of Contents

Sign up for more exam tips and discounts



How To Pass SPS Exam on the First Try
ScrumPrep

SPS Exam Guide

The Scaled Professional Scrum (SPS) exam is a challenging certification that validates one’s knowledge and expertise in scaling Scrum. It is a globally recognized certification that offers numerous benefits to individuals and organizations. However, passing the exam is not easy and requires adequate preparation and dedication. In this article, we will provide you with tips and strategies on how to pass the SPS exam and earn your certification. Table of Contents Understanding the SPS Exam Purpose and Structure The SPS exam is designed to assess your knowledge of the Nexus Framework and your ability to apply Scrum in large-scale environments. The exam consists of multiple-choice questions, which you must complete within a specified time. A passing score earns you the

Read More »

Related Products

LIMITED TIME SALE!
SPS Practice Tests - ScrumPrep
Master the art of scaling product development with multiple Scrum Teams working together. Easily pass the exam and become a certified SPS professional.
  • 182 SPSâ„¢ exam sample questions
  • Five complete exams with up to 40 questions each
  • Real exam mode with unlimited question combinations
  • Questions developed by experienced Scrum exam experts
  • Updated to the current SPSâ„¢ 2024 exam
  • Pass Guarantee to ensure your success

You cannot copy content of this page

$35 Exam Preps

Sale Ending Soon

Day
Hour
Min
Sec
Offer Expired
Add Your Heading Text Here