The Sprint Review is a key event in the Scrum framework, providing an opportunity for the Scrum Team and stakeholders to inspect the Increment and adapt the Product Backlog if needed. It is an essential time for gathering feedback and ensuring the product is on the right track to meet business goals.

Exam Question

Which topics should be discussed in the Sprint Review?
(choose the best answer)
A. The Scrum process, and how it was used during the Sprint.
B. The product Increment.
C. Coding and engineering practices.
D. All of the above.

Correct Answer

B. The product Increment.

Explanation

Correct Answer

B. The product Increment:
The primary focus of the Sprint Review is to inspect the product Increment that has been completed during the Sprint and to gather feedback from stakeholders. This event is centered around the product itself, discussing what was done, what was not done, and how the product is evolving.

Why the Other Options Are Less Appropriate

A. The Scrum process, and how it was used during the Sprint:
While it’s important to reflect on the Scrum process, this is typically the focus of the Sprint Retrospective, not the Sprint Review. The Sprint Review is more about the product and less about the process.

C. Coding and engineering practices:
Discussions about coding and engineering practices are better suited for the Sprint Retrospective or technical discussions within the team. The Sprint Review is not the place for deep dives into technical practices but rather for reviewing the product Increment with stakeholders.

D. All of the above:
While all these topics are important, the Sprint Review is specifically aimed at reviewing the product Increment and gathering feedback. The other topics listed would be more appropriate for the Sprint Retrospective or internal team discussions.

Relevance to the PSD Exam

Understanding the purpose of the Sprint Review is essential for the PSD exam. This knowledge helps clarify what should and should not be the focus during this event, ensuring that the Scrum Team uses this time effectively to gather valuable feedback and refine the Product Backlog.

Key Takeaways

  • The Sprint Review focuses on inspecting the product Increment and gathering stakeholder feedback.
  • Other topics, like process improvement and coding practices, are better suited for the Sprint Retrospective.

Conclusion

The Sprint Review is a vital event in the Scrum process that focuses on reviewing the product Increment with stakeholders and adapting the Product Backlog as needed. It ensures that the product is evolving in line with stakeholder expectations and business goals. For more insights and preparation tips for the PSD exam, visit our Professional Scrum Developer PSDâ„¢ Exam Prep.

Sign up for more exam tips and discounts



You cannot copy content of this page

$35 Exam Preps

Sale Ending Soon

Day
Hour
Min
Sec
Offer Expired
Add Your Heading Text Here