Answering: “When is a Product Backlog item considered complete?”

Table of Contents

Understanding the Definition of Done in Scrum

In Scrum, it is crucial to have a clear and shared understanding of when a Product Backlog item is considered complete. This article explores the concept of the Definition of Done (DoD) and its importance in ensuring the delivery of valuable and potentially releasable Increments.

Exam Question

When is a Product Backlog item considered complete?
(choose the best answer)
A. At the end of the Sprint.
B. When the item passes all acceptance criteria.
C. When the item meets the Definition of Done.
D. When the item has gained product sponsor approval.

Correct Answer

C. When the item meets the Definition of Done.

Explanation

Correct Answer

C. When the item meets the Definition of Done:
In Scrum, a Product Backlog item is considered complete when it meets the Definition of Done (DoD). The DoD is a set of criteria that ensures the work is fully finished and potentially shippable. It provides a clear and shared understanding among the Scrum Team of what it means for work to be complete.

Incorrect Answers

A. At the end of the Sprint:
While work is typically reviewed at the end of the Sprint, completion is not solely determined by the Sprint’s conclusion. The DoD must be met for an item to be considered done.

B. When the item passes all acceptance criteria:
Acceptance criteria are important, but they are usually specific to each Product Backlog item. The DoD encompasses broader criteria that apply to all items, ensuring consistency and completeness.

D. When the item has gained product sponsor approval:
Product sponsor approval might be part of the process, but it is the adherence to the DoD that officially marks the completion of a Product Backlog item.

Responsibilities in Scrum

  • Product Owner: The Product Owner ensures that the Product Backlog items are clearly defined and understood by the team. They work with the Scrum Team to refine items and ensure they meet the DoD before being marked as complete.
  • Scrum Master: The Scrum Master facilitates the team’s adherence to the DoD, ensuring that the team understands and applies it consistently.
  • Developers: The Developers are responsible for completing the work according to the DoD. They ensure that every increment meets the DoD, ensuring quality and completeness.

Relevance to the PSPO I Exam

Understanding the concept of the Definition of Done is crucial for the PSPO I exam. It ensures that candidates appreciate the importance of quality and completeness in delivering potentially releasable Increments. This knowledge helps in managing expectations and maintaining transparency with stakeholders.

Key Takeaways

  • The Definition of Done (DoD) is a set of criteria that ensures work is fully complete and potentially shippable.
  • A Product Backlog item is considered complete only when it meets the DoD.
  • The DoD creates a shared understanding of what it means for work to be done, ensuring quality and consistency.

Conclusion

The Definition of Done is a critical aspect of Scrum, ensuring that every Product Backlog item is completed to a high standard. By adhering to the DoD, Scrum Teams can deliver valuable and potentially shippable increments consistently. For more insights and preparation tips for the PSPO I exam, visit our PSPO I Exam Prep.