Handling Mid-Sprint Changes
Managing changes effectively is crucial in Scrum. This article explores how a Product Owner should handle new feature requests that arise in the middle of a Sprint, specifically for the PSPO I exam.
Exam Question
In the middle of the Sprint, the customer decides that there are 2 new features she wants. The Product Owner could:
(choose the best answer)
- A. Have the Developers add these features to the current Sprint
- B. Have the Scrum Master add these features to the current Sprint
- C. Introduce these features at the next Sprint Planning meeting
- D. Introduce these features at the next Daily Scrum
Correct Answer
C. Introduce these features at the next Sprint Planning meeting
Explanation
Correct Answer
C. Introduce these features at the next Sprint Planning meeting:
Introducing new features during the current Sprint can disrupt the team’s focus and the Sprint Goal. In Scrum, changes to the Sprint Backlog are managed through the Product Owner’s role, and new requirements should be introduced at the next Sprint Planning meeting. This ensures that the team can properly plan, estimate, and prioritize the new features along with other backlog items.
Incorrect Answers
A. Have the Developers add these features to the current Sprint:
Adding new features mid-Sprint without proper planning can lead to disruptions and may compromise the Sprint Goal. This approach contradicts the principle of maintaining a stable Sprint Backlog during the Sprint.
B. Have the Scrum Master add these features to the current Sprint:
The Scrum Master does not have the authority to change the Sprint Backlog. This responsibility lies with the Product Owner, and changes should be introduced in a structured manner during Sprint Planning.
D. Introduce these features at the next Daily Scrum:
The Daily Scrum is not the appropriate event for introducing new features. It is a time for the team to inspect progress toward the Sprint Goal and adapt their plan for the day.
Responsibilities in Scrum
- Product Owner: Accountable for managing the Product Backlog and ensuring that new features are introduced at appropriate times, such as during Sprint Planning.
- Scrum Master: Facilitates Scrum events and ensures the Scrum framework is followed but does not directly add or manage Product Backlog items.
- Developers: Focus on achieving the Sprint Goal with the current Sprint Backlog and collaborate with the Product Owner during Sprint Planning for any new requirements.
Relevance to the PSPO I Exam
Understanding how to handle mid-Sprint changes is essential for the PSPO I exam. This knowledge ensures that Product Owners can maintain focus and stability within the Sprint while effectively managing new requirements.
Key Takeaways
- New features should be introduced at the next Sprint Planning meeting to maintain focus and stability during the Sprint.
- The Product Owner is responsible for managing the Product Backlog and introducing changes in a structured manner.
- The Scrum Master facilitates the process but does not have the authority to change the Sprint Backlog.
Conclusion
Handling new feature requests in the middle of a Sprint requires careful management to avoid disrupting the team’s focus and the Sprint Goal. The Product Owner should introduce new features at the next Sprint Planning meeting. For comprehensive preparation and practice exams, check out PSPO I Exam Prep to enhance your understanding and application of Scrum principles.