Best Approaches for Scrum Teams to Produce Valuable Increments
In Scrum, the ability to deliver valuable Increments is crucial for ensuring continuous improvement and meeting the goals of the product. The approach a Scrum Team takes in organizing their work directly impacts the quality and value of the Increments they produce.
Exam Question
Which approach is best for Scrum Teams in order to produce valuable Increments?
(choose the best answer)
A. Each Scrum Team is accountable for developing functionality from beginning to end.
B. Each Developer works only on the component where they feel they can contribute.
C. Each Scrum Member works only as an independent layer of the system.
D. Each Scrum Team works on an independent set of components.
Correct Answer
A. Each Scrum Team is accountable for developing functionality from beginning to end.
Explanation
Correct Answer
A. Each Scrum Team is accountable for developing functionality from beginning to end:
This approach ensures that each Scrum Team is responsible for delivering a complete and potentially releasable Increment at the end of every Sprint. It promotes cross-functional collaboration within the team, where all necessary skills to deliver a complete Increment are present. This approach aligns with Scrum’s emphasis on producing valuable Increments that meet the Definition of Done.
Why the Other Options Are Less Appropriate
B. Each Developer works only on the component where they feel they can contribute:
This approach can lead to silos within the team, where Developers focus only on their areas of expertise rather than collaborating to deliver a complete Increment. It can also hinder the team’s ability to produce integrated and valuable Increments.
C. Each Scrum Member works only as an independent layer of the system:
Working in independent layers can create dependencies and delays in integration, which might prevent the team from delivering a potentially shippable product Increment at the end of the Sprint.
D. Each Scrum Team works on an independent set of components:
This approach could lead to fragmented Increments that do not provide a cohesive value to the customer. It contradicts the principle of creating a “Done” Increment that is fully integrated and potentially shippable.
Relevance to the PSD Exam
Understanding the importance of full accountability in developing functionality from beginning to end is key for the PSD exam. It emphasizes the need for cross-functional teams that can deliver complete and valuable Increments.
Key Takeaways
- Cross-functional Teams: Essential for delivering fully integrated and valuable Increments.
- Accountability: Each Scrum Team should be responsible for delivering complete functionality.
Conclusion
To ensure the delivery of valuable Increments, Scrum Teams should be accountable for developing functionality from beginning to end. This approach fosters collaboration, integration, and the production of high-quality Increments. For more information on preparing for the PSD exam, visit our Professional Scrum Developer PSDâ„¢ Exam Prep.